Start at the bottom of the wall at one end.
How to nail cedar shake siding.
Begin the installation by wrapping the house with a waterproof membrane either 15 to 30 pound felt or semi permeable house wrap.
Use galvanized nails or staples for most of the job but stainless steel nails are the best choice wherever the heads will show.
Each row overlaps the.
Adjust the stapler so it drives the staples just flush and does not indent them.
Apply overlapping horizontal rows of building paper onto the shear wall using a staple gun with 3 8 inch staples.
This is when each piece of cedar siding covers half of the one below it much like staggering and layering on cedar siding on top of one another to provide a scale like appearance.
Drive the staple flush with a hammer.
Go back and nail subsequent nails along the top edge of this cedar shake siding piece.
Bevel siding should be face nailed to studs with 1 1 4 inch penetration into solid wood using one nail per piece spaced at a maximum of 24 inches on center.
Place nail just above the overlap.
How to install cedar shingle siding.
Align the thick lower edge of a cedar shake at the lower edge.
Step 4 choices of design.
You can hand nail with galvanized casing nails but most builders use something like a bostich trim nailer for speed.
Install the windows and door jambs so you can trim the doors windows and corners of the house with wood trim.
Use two fasteners to apply each certi label shingle or shake.
Apply both nails 3 4 inches from the edge of each shake or shingle and about 1 1 2 inches above the exposure line.
Where possible the bottom of the board that is placed across the top of the windows should coincide with the window cap.
The idea is to avoid double nailing the board which will cause cracks when it shrinks.
When you hit a stud the staple may not sink in completely.
Nails should be long enough to penetrate underlying materials in the cedar shingles at least 3 4 inches or all the way through.
Nails are used to secure each shake and spaced accordingly so that the next line of shakes will cover the preceding line.